Maria

Openwork tunic with knitting needles

Click For Crochet Abbreviations List

Sizes: 36/38 (40/42) 

You will need: 450 (500) g light gray and 50 g. Mauga dark gray yarn (90% cotton, 10% polyamide. 125 m / 50 g); Knitting needles number 3.5 and number 4.5; hook number 4; rubber thread. 

Strip with holes from p. 5: knit according to scheme 1. which shows only persons. r., in izn. R. knit loops on the pattern, knit knit izn. Knit 1 rapport and repeat from 1st to 4th p. 

Openwork pattern of 17 p.: Knit according to scheme 2. which shows only persons. p .. in out. R. all loops and nakida knit izn. Repeat 1 time from the 1st to the 24th p .. then repeat from the 11th to the 24th p.

Gum: the number of loops after the 1st p. multiple 5 + 2 chrome. Start with 1 chrome .. 

* 1 from .. 3 persons., 1 from., Repeat from * finish 1 chrome .. at the same time in the 1st p. knit over the openwork pattern 2 x 2 p. together persons., as indicated in figure 2 (row A). In izn. R. knit loops on the pattern. 

Striped pattern with holes: the number of loops is a multiple of 5 + 2 chrome. Knit as a strip with holes from 5 p., Repeating between chrome. rapport 

The sequence of alternation of patterns: chrome .. 17 p. Openwork pattern. 5 p. Strip with holes, repeat from * 3 more times, finish with 17 p. Openwork pattern, chrome .; for size 40/42: chrome., 5 p. strip with holes. 17 p. Openwork pattern, repeat from * 4 more times, finish 5 p. Strip with holes, chrome. 

Knitting density

The sequence and striped pattern with holes, knitting needles №> 4.5: 20.5 p. And 27 p. = 10 x 10 cm: gum, needles number 3.5: 23 p. And 35 p. = 10 × 10 cm

The back: on the spokes number 4.5 dial dark gray thread 107 (117) p. And tie 1 w. R. individuals. (this series is not taken into account with further account). Then knit with a light gray thread in the specified sequence. After 35 cm = 94 p. from the typesetting edge, go to the needles No. 3.5 and knit a dark gray thread with an elastic band and a waist strip, while at the same time changing the color, knit the 1st p. individuals. After the 1st p. 97 (107) p. are at work. At the height of the waistline is 4 cm = 14 p. go to the spokes number 4.5 and continue to work with a light gray thread with a striped pattern with holes, while at the same time changing the color, knit the 1st p. individuals. At the same time, from the waist bar, add to give shape on both sides in each 10-m p. 5 x 1 p. = 107 (117) p., Including the added p. In the pattern. Through 24.5 cm = 66 p. from the slat waist close for bevels of the sleeve / shoulder on both sides 3 p. and in each 2nd p. 6 x 3 and 3 x 4 p. (1 x 3 and 8 x 4 p. ). After 32 cm = 86 p. to close the remaining 41 p. from the waist plank; meanwhile, the average 33 p. form a neckline, the outer 4 p. on each side belong to the shoulders.

Before: knit the same way, but for a deep V-neck cut to close in the 1st p. from the strap waist middle p. and both sides finish separately. For a slant cut, close from the inside edge alternately in each 4th and 6th p. 16 × 1 p. Through 32 cm = 86 p. from the slat waist close the remaining 4 p. shoulders on each side. 

Assembly: seam the sleeves / shoulders. To tie a neckline of 1 circular p. Art. b / n light gray and "crawfish stride" (= st. b / n from left to right) dark gray thread. Run side seams to the end of the waist strap. Tie the edges of the sleeves as a neckline. If necessary, draw a rubber thread into the waist bar.














Post your comment

Information!  You need to be a member to comment. You can easily sign up from here.

0 comments